Suçatı HPP Final and Detailed Design Projects

Project Location

The Suçatı Hydroelectric Power Plant (HPP) Project is located in the Western Black Sea Region, on the section of the Filyos River known as the Yenice River. The project area is situated approximately 12 km west of Karabük city center and about 14 km east of Yenice District.

Project Facilities

The structures included in the project consist of the following components:

  • Suçatı Regulator
  • Energy tunnel
  • Surge tank
  • Powerhouse building

Project Characteristics

Design Discharge 100 m3/s
Number of Units 3 units
Turbine Type Francis
Regulator Type Radial Gate
Number of Gates 3 units

Services Provided

  • Preparation of the Final Design Projects
  • Preparation of the Detailed Design (Implementation) Projects